|
1
|
|
|
2
|
|
|
3
|
|
|
4
|
|
|
5
|
|
|
6
|
|
|
7
|
|
|
8
|
|
|
9
|
|
|
10
|
- A37:
- - established a process for the
Public Utilities Commission to open a rulemaking docket to implement A37
by April 1, 2005.
-
- requires the PUC to
complete the rulemaking proceeding by March 1, 2006.
- - was modified slightly by the legislature May 2005.
|
|
11
|
- November 2, 2004- Colorado
citizens pass A37.
- December 10- 50 representatives of the solar community meet.
- February 22, 2005- 90 representatives of the solar community meet
with utilities.
- February: RE community (Core37)
presents draft rules to Xcel.
- March 4, 10- COPUC Staff conducts informal workshops.
- March 29- Draft rules issued by COPUC for comment.
- May 18- Written Comments Filed at PUC
- June 25- Xcel says, “Let’s
Talk”- Petitions PUC to delay hearings.
- July 11- PUC public witness hearing- 25 attend.
- Mid-July to mid-August- In-depth
negotiations.
- August 15- Partial consensus
rules filed.
- August 30, 31- Technical and public hearing- 50 citizens testify.
- September 15- Final written comments filed.
- October 7- Commissioners deliberated.
|
|
12
|
- The PUC developed a written record stemming from the public and
technical hearings held on August 30-31.
- PUC held a deliberative meeting on Friday, October 7th. The meeting
lasted 3.5 hours.
- The Commissioners and Staff worked from a 60+ page document
that contained suggested wording from Staff, and comments/wording
from other parties (Core37, Xcel, Aquila, Tri-State, etc).
- PUC Staff presented their recommendations on the A37 rules.
- The Commissioners responded, questioned, discussed, and voted on the
recommendations and modifications. Very little dissent among the
Commissioners.
|
|
13
|
- The PUC approved all of the issues where the parties had reached
agreement (definitions, environmental requirements, net metering,
interconnection, timing, RECs, reporting, etc.)
- The rules will include the
legislative intent of voters embodied in the language on the ballot
itself (saving customers and businesses money, improving the
environment, increasing generation diversity, saving water, improving
rural economies, and attracting new businesses and jobs)
- Rebates will be fully retroactive to 1/1/2004 (not 12/1/2004 as proposed
in compromise rules).
- Where Xcel has a contract with a generator that does not mention RECs
-e.g., many of the hydro facilities in Boulder- RECs for compliance are
created and belong to Xcel.
|
|
14
|
- The PUC:
- - accepted a compromise allowing flexibility
on timing over the 9 year compliance period.
- - accepted a standard rebate
offer for solar systems. It is a hybrid rebate of $2/W + the utility
purchase of the anticipated REC value over a 20 year period (~$2.50/W).
Equals ~$4.50/W.
- - adopted true net metering (a
single bi-directional meter) for systems under 10kW.
- - adopted interconnection
standards. Solar systems that are “UL” or similarly rated can be
interconnected to the electric grid without expensive studies.
|
|
15
|
- The concept of the RE and solar rebate pool of money being larger than
the money raised by a 1% rate hike was accepted. Expect the savings from
wind to be used as a credit to apply against the 1% rate cap.
- Consider wind farms in three categories:
A. The Lamar wind farm (and any other existing wind
farm).
B. The remaining 60 MW wind farm in the 500 MW wind RFP, and
any renewables in the All-Source RFP. That is, wind farms not yet
built, but in progress with Xcel, and approved through the PUC as part
of the LCP process.
C. Future wind farms after the All-Source.
Core37 asked that the savings from A B & C be added to the
pool for solar rebates (and likely reduce the rate impact below the 1%
cap).
Xcel would count only C.
The PUC chose B & C for counting savings to be placed in
the solar rebate dollar pool. A, B & C would count for meeting the
renewable energy standard.
|
|
16
|
The charge, if any, for paying for the RPS, will be appear as a separate
line item on the customers’ bills.
- There may be a substantial net credit from wind, as a result of the now
extremely high cost of gas-fired generation.
A 10% cap of Xcel's administration costs was imposed. The cap may
be waived by the Commissioners.
- The idea of a third party administrator was rejected as too expensive.
- Specific rules will be drafted to help encourage greater transparency. The PUC acknowledged A37
as the voice of the public, and citizens have a right to know that the
RPS is being met. If direct transparency is not allowed for
confidentiality reasons, then a degree of transparency may likely be
available through an A37 advocate (e.g., Western Resource Advocates).
|
|
17
|
- Special Definitions settled
- Overview PUC favors RE position
- Applicability settled
- Municipal and Cooperative Utilities settled
- Renewable Energy Standard settled
- Competitive Bidding settled
- Environmental Impacts settled
- QRU Plan or Administrator PUC
favors utility position
- Solar Electric Generating Technologies
- Interconnection + Net Metering + Standard Rebate Offer settled
- Renewable Energy Credits settled
- Cost Recovery
- Retail Rate Impact PUC
primarily favors RE position
- Annual Reports settled
- Commission Actions settled
|
|
18
|
- Initial rules will be issued in mid-November.
- Up to 20 days after the rules are mailed, parties (the public, in
rulemaking) may apply for triple-R (re-hearing, re-argument, or
reconsideration). Triple-R permits requests to the PUC to clarify or
include language-- but not to rehash old arguments.
- For example, it may be reasonable to bring up the issue of the
separate line item on a bill going negative if that procedure is
not covered in the initial rules. It would not be OK to ask the PUC
to revisit their decision on the third party administrator.
|
|
19
|
|
|
20
|
- The PUC will consider revisions to the current Least Cost Planning (LCP)
rules for competitive electric resource acquisition.
- This is an opportunity to address
incentives, transparency, evaluation of demand and supply side
resources, and A37 values.
- The commitment to reopen the LCP rules was a concession resulting from
the Dec. ‘04 Settlement Agreement regarding the 750MW Comanche plant to
be built in Pueblo.
- As required by the settlement, Xcel filed an application to open the LCP
docket.
- A workshop to scope out a proposed procedure is scheduled for October
28, 9 a.m.
|
|
21
|
- Craft policies in Colorado to help build transmission lines that will
bring new wind projects to markets?
- Both the Texas and Minnesota legislatures have required their utilities
(including Xcel) to:
- identify wind resource development areas,
- plan for providing the transmission necessary to meet their state
renewable standards and goals,
- report back to the legislature on those plans within short time frames.
|
|
22
|
- Are electric and gas utility efficiency policies resulting in the
requisite contribution to Colorado’s economic development?
- Xcel has a commitment of 40MW/year of electric DSM for 8 years. Capped
at $190M.
- There are currently no gas utility DSM programs in place in Colorado.
- The PUC has scheduled a Gas Roundtable on Monday, November 7 at 9:30
a.m.
- House Speaker Romanoff has scheduled an energy roundtable for Tues, Nov.
8, Details TBD.
- Mayor Hickenlooper is co-sponsoring the Denver World Oil Conference (peak
oil) on Nov. 10-11.
- An Interconnection and Net Metering Workshop for Colorado co-ops and
munis is planned for mid-December, Details TBD.
|
|
23
|
|
|
24
|
|